A
VÖGELE SUPER 1900 with AB 500 Extending Screed in TP2
Version on the Scene in the Hunsrück Region, Germany.
A Roundabout on a Hilltop
Building Site:
German contractor Wust & Sohn of Simmern built a roundabout
at the junction of the B48 and B41 Federal highways near Bad
Kreuznach, Hunsrück.
Geometry:
Outer Radius up to 20m; Inner Radius 12m.
The site on the hilltop included inclines and slopes.
Construction:
Part of the specification was that the 8m wide road should
be paved without joints. The VÖGELE paver came with 2
bolt-on extensions fitted. Although the SUPER 1900 operated
under the most severe conditions due to the slope on the site,
the pavement quality achieved by the machine was excellent
and fully complied with the expectations. A precondition for
achievement of the excellent quality was use of the full package
of VÖGELE technology (steering by potentiometer, NIVELTRONIC
Automated Grade and Slope Control, Screed Assist for added
traction).
Mix:
Stone mastic asphalt (SMA 0/11S PmB) with polymer modified
binder.
Paver:
VÖGELE SUPER 1900 with AB 500 Extending Screed in TP2
version fitted with 2 bolt-on extensions 75cm each. Pave width
was 7.5m to 8m.